WASHINGTON, Dec. 27 /PRNewswire-USNewswire/ -- Twelve primary
healthcare centers (PHC), designed to provide essential medical care to
people in underdeveloped urban and rural areas in the Dhi Qar and Muthanna
provinces, will open by June 2007, according to Gulf Region South (GRS)
District officials.
(Photo: http://www.newscom.com/cgi-bin/prnh/20061227/UNW004 )
Construction on 55 facilities in the nine southern provinces halted
when the primary contractor, Parson's Corp., was terminated last year, but
GRS re- awarded the contracts six months ago, according to Mike Osborne,
Dhi Qar resident engineer.
"The clinics were in various stages of construction when Parsons left,"
he said. "Some were weeks ahead of the others."
Lt. Col. Dale Johnson, Camp Adder area engineer, noted that the centers
under his watch -- eight in Muthanna and four in Dhi Qar -- exist in an
increasingly dangerous security environment and this makes them difficult
to build.
"I've got two in the area that are nearly finished," he said, "one in
Muthanna and one in Dhi Qar. Both have been built by the same contractor
and will be finished in the next 30 days."
Johnson said that despite the challenges of building the facilities, he
reaps personal rewards from knowing that GRS has provided the community
with something that is "uniquely good. They don't get this level of medical
care or service," he said. "Not outside of hospitals anyway."
"These (centers) will be great for preventative care -- and we have
separate contracts for equipment and medical supplies -- more modern than
anything they have ever had -- to stock these places for the first time,"
he said.
Of the three PHC designs, the centers under the Adder Area Office's
purview fell into one category -- the smaller design, Osborne said. "That's
because, in the Nasiriyah area, there are major hospitals available to the
people," he said. "Type A and B -- those are the smaller facilities. Type C
facilities are larger and have emergency, trauma and maternity centers."
All three centers have dental facilities, X-ray departments and
instructional units with one physician in residence. The Type C healthcare
centers will have two physicians and will be built in more rural areas,
according to Osborne.
"Nasiriyah is obviously a city and has core sections which are in the
less fortunate areas," he said. "That's where we have built the A and B
centers -- in the poorer sections of town. Because of the availability of
the local hospitals, these centers typically do not have emergency
services."
The cost for the healthcare centers runs between $500,000 to $600,000
for Type A and B centers, and between $650,000 and $1 million for Type C.
"Empirically," Osborne said, "we are running 37-38 percent completed on
these contracts. There is one in Nasiriyah that is the last one to come
back online in GRS - its further behind relative to the others."
Most of the contracts awarded are of 180-210 day duration. Some work
has been "painfully slow" for a number of reasons.
"We don't finance projects here -- we build the project and monitor the
production. Typically in the States, a big contractor has to post a bond
stating that he has enough funding to float the project. In Iraq, it's a
different delivery concept for some contractors."
He added that getting experienced contractor laborers has been a
challenge as well.
"You know, they lack middle management here," Osborne said. "It reminds
me of a lot of when there are lay-offs in the coal mines and then, well,
everyone is a carpenter. It seems like if you work around construction or
know someone who does, you are an engineer. Not necessarily in educated
tech sense, but maybe in the foreman sense. But you do have the educated
engineers -- guys running these jobs are young guys out of college trying
to move up the ladder -- instead of crusty old construction workers like me
out here."
Most of the PHCs will be completed around the May-June timeframe,
Osborne said, but added that other contracts for equipment and services,
such as electrical and plumbing, also have to be completed.
"Coordinating all that stuff is something that doesn't translate into
Arabic. It is hard to get across the idea of doing concurrent work or doing
work in a logical sequence to make these things come on line at the end,"
he said.
"But these PHCs are going to be a little more technical so you have to
have more sophisticated electrical and mechanical systems. For example, you
have alarms, things that will trigger a generator so the air conditioning
remains constant."
Training people to operate the systems when the clinics are handed over
to the Ministry of Health is the key to their successes, Osborne said.
"Training is required for all these things -- the systems and all
that," he said. "And we are working with the Ministry of Health about
providing or dedicating staff to operate these systems so these clinics
will remain operational."
"The construction that I have seen so far on these facilities is some
of the best I have seen in Iraq," Johnson said, "And the equipment they are
getting is an added bonus to the utility of these clinics. The (healthcare
centers) look and smell great."
Note: Betsy Weiner is a public affairs specialist for the Gulf Region
South District, U.S. Army Corps of Engineers, Iraq. For more information,
please contact James Bullinger, public affairs officer, at (540) 665-2656.
Email requests can be sent to GRD Public Affairs at CEGRD.PAO@
tac01.usace.army.mil. For more information on the U.S. Army Corps of
Engineers in Iraq, visit http://www.grd.usace.army.mil.
SOURCE U.S. Army Corps of Engineers
back to top
Related links: http://www.grd.usace.army.mil
Photo Notes: NewsCom: http://www.newscom.com/cgi-bin/prnh/20061227/UNW004 PRN Photo Desk, photodesk@prnewswire.com
CONTACT: James Bullinger of the U.S. Army Corps of Engineers, +1-540-665-2656
|